VISY BEVERAGE FACTORY
  • Job: VISY Beverage Factory [2012 – ECS Solutions]
  • Client: ECS Solutions
  • Tonnage: 700t
  • Date Commenced: 27/02/12
  • Duration Of Scope: 6 Weeks
  • Specification:
  • Welding: AS1554.1 SP
  • Fabrication: AS4100
  • Protective Coating: Sandblast (class 1)
  • Paint System: Zinc Phosphate Primer
Description:

ATW Group was awarded the contract for the construction of a 17,000m2 Beverage Can Plant at Yatala for VISY in December 2011.

Our 6 week site works program commenced late Febuary and remained on track until completion