[2012 - LEDA HOLDINGS]
RIVERLINK CARPARK
  • Job: Riverlink Carpark [2012 – LEDA Holdings]
  • Client: LEDA Holdings
  • Tonnage: 800t
  • Date Commenced: May 2012
  • Duration Of Scope: 6 months
  • Specification:
  • Welding: AS1554.1 SP
  • Fabrication: AS4100
  • Protective Coating: Sandblast (class 2.5)
  • Paint System: Inorganic Zinc
Description:

ATW Group was awarded the contract to extend the capacity of Ipswich Riverlinks Shopping Centre carpark from it’s already large 2000 spaces.

The new additon will see an additional 300 spaces added by way of an intermediate mezzanie level between ground and the existing large carpark deck.

ATW Group fabricated and installed the original deck – So it made sense we dig out the old models, enabling a very quick steel detailing turnaround with little to no site measure.

All steel was erected by our own telehandler, as head height between the original deck didn’t allow traditional for methods. Even with this small challenge we were able to complete this project well within LEDA’s expectations.